By Townhall Chicago News Staff
The Chicago Department of Transportation completed installation of the new west leaf of the Lake Street Bascule Bridge on Thursday, restoring normal Green and Pink line train service at 4 a.m. after weeks of disruptions.
The milestone ends a service interruption that had closed the Green Line between Clinton and Clark/Lake stations and suspended Pink Line service around the Loop while crews replaced the 110-year-old bridge’s deteriorating west leaf. The project is part of a two-year rehabilitation of one of the city’s most heavily used multimodal river crossings.
The new, prefabricated west leaf was assembled off-site and transported up the Chicago River by barge, according to a joint CDOT and CTA news release issued Thursday. Crews removed the existing leaf, then positioned and installed the replacement. Work also included rebuilding CTA tracks, ties, guard systems and walkways, reconnecting and testing power and signal systems, and running test trains before regular service resumed.
“CDOT thanks riders for their patience throughout the disruption as crews completed this critical bridge work,” the release said.
CDOT and CTA coordinated closely throughout the closure, with CTA using the planned interruption to complete additional repairs at the Loop and Lake Junction over the preceding weekend, according to the release.
Built in 1916, the Lake Street Bridge is a double-deck, double-leaf movable bridge that accommodates river traffic, carries vehicles, pedestrians and CTA buses on its lower level, and Green and Pink line trains on its upper level. The two-year project aims to fully rehabilitate the structure so it can serve the city for generations while maintaining its historic character, the release said.
Installation of the bridge’s east leaf is planned for spring 2027, which will require similar disruptions to Green and Pink line service. CDOT and CTA said they will share details about the timing and anticipated impacts as the work approaches.
The bridge’s lower level remains closed to vehicles and pedestrians while rehabilitation continues. The full reopening is expected in January 2028, according to the release.
The restoration of service comes after CDOT announced a two-day extension of the original closure timeline on Oct. 25. The additional time was needed to complete alignment and stabilization of the new bridge components, the agency said.
Green Line riders traveling between the West Side and the Loop and Pink Line commuters from neighborhoods including Pilsen and Lawndale bore the brunt of the disruption, relying on shuttle buses and alternative routes for more than two weeks.
The Lake Street Bridge project is one of several major bridge rehabilitation efforts underway in Chicago. CDOT has identified dozens of aging bridges across the city in need of structural work.
Riders can check real-time service status and plan trips at transitchicago.com.
Source: CTA Press Releases